Westwood Community School District
Westwood Community School District
Additions & Renovations
SCOPE & SIZE
Construction of a new softball and baseball concession building, additions and renovations to the existing football concession building, and reroofing of approximately 45,500 SF of the school's 2001 building additions.
PROJECT DURATION
6 Months
LOCATION
Sloan, IA
PROJECT OVERVIEW
W.A. Klinger was selected by Westwood Community School District as Construction Manager at Risk (CMr) in June 2024, with pre-construction services beginning immediately. The project included reroofing designated portions of the main school building, construction of a new softball and baseball concession facility, and additions and renovations to the existing football concession building.
Construction began in May 2025 and was completed in October 2025. W.A. Klinger self-performed several key scopes of work, including concrete foundations and concrete paving, demolition, rough carpentry, finish carpentry, insulation and drywall, as well as overall project management and supervision.
KEY PROJECT FEATURES
New softball and baseball concession building
Football concession building additions and renovations
Reroofing of approximately 45,500 SF of existing facilities
CMaC delivery method with pre-construction services
Self-performed concrete foundations and concrete paving, demolition, rough carpentry, finish carpentry, and insulation and drywall